FG to shutdown Third Mainland Bridge for another 72 hours from Friday

0

The Federal Controller of Works Lagos, Mr Olukayode Popoola on wednesday announced another three days of total shutdown of the Third Mainland Bridge for another round of delicate expansion joints replacement.

Popoola told the News Agency of Nigeria (NAN) on telephone that the shutdown would take effect from midnight on Friday to midnight of Monday, Feb. 1.

He explained that construction works had reached the stage for casting concrete on additional three expansion joints, hence the need to stop all movements on the bridge that could cause vibrations.

He said that the 72 hours closure was to ensure that the concrete sets properly during the curing process’ to make the rehabilitation works perfect and durable.